Query
I want to prepare company change documents in advance. How do I enter a future date on the company documents when preparing company changes?
Solution
When entering the Company Changes, input the future date into the transaction date field.
- Beside these changes, flag the print option ().
- Click .
CAS 360 will now display the Document Production screen.
Users are able to future date company change documents in CAS 360.
However the following needs to be noted:
- The document date of the ASIC form cannot be prior to the date of change
- The ASIC form cannot be lodged before the date of change. (see V117)
In the Document Production screen, the document date (signing date) cannot be dated before the company change date.
In the document production screen beside the document, click
In the document date field, change the date to be on or after the date of change.
Click